The Labour Court recommended increasing the number of Team Leaders to four in Areas 4 and 8 at Bord Na Mona’s Blackwater Works, pending a wider review. The recommendation, dated 17 April 2002, followed a dispute with the Irish Congress Of Trade Unions over staffing levels. Bord Na Mona argued staffing should reflect operational needs and pointed to investment of more than €5 million in plant and machinery. The union said the staffing framework called for four Team Leaders in each area.
Labour Court recommends four Team Leaders at Bord Na Mona’s Blackwater Works