Glenmore Generation Limited fined €3,000 over odour-control emissions
- Who
- Glenmore Generation Limited
- Outcome
- Fined €3,000
- Where
- Ballybofey, Co Donegal
- Court
- Letterkenny District Court
- Court date
- 4 March 2026
- Source
- Environmental Protection Agency · Court case
The company was convicted at Letterkenny District Court after emissions from an odour-control stack exceeded its licence limit.
Glenmore Generation Limited was convicted and fined €3,000 at Letterkenny District Court after emissions from an odour-control stack exceeded a limit in its industrial emissions licence. The case was heard on 4 March 2026 before Judge Daly, according to the EPA prosecution notice.
The charge related to emissions to air at the licensed site’s A2-2 odour-control stack on or about 8 August 2024. The notice said the emissions exceeded the licence’s limit of 1,000 OuE/m³.
The company pleaded guilty to breaching the licence condition. Judge Daly, having heard the evidence, convicted Glenmore Generation Limited and imposed the €3,000 fine. Agency costs were also agreed, according to the EPA prosecution notice.
The EPA prosecution notice states that the matter is currently under appeal.