Recorded milestones for this application. A permission is not evidence that building work has started.
Grant recordedSource: Council portal
Council portal · source SHA-256: 49ad93ea8c69123d4570e7557b959e69acf491e47f4ffce88e38dac78ccb9648 · field: finalGrantDate
Application registeredSource: Council portal
Council portal · source SHA-256: 49ad93ea8c69123d4570e7557b959e69acf491e47f4ffce88e38dac78ccb9648 · field: registrationDate
What changed
First retained observation; this does not establish that the application is new.
Observed: 21 September 2026. This describes our archive, not an application event date.
Why it matters locally
The proposal concerns Terenure Synagogue, 32A Rathfarnham Road, Rathfarnham, Dublin 6W. Proposal excerpt: “20. The construction of the proposed development shall be managed in accordance with a Construction Management Plan, which shall be submitted to, and agreed in writing with, the planning authority prior to commencement o…” Demolition is included in the proposal description.
Individual document links are not available in this retained record. Use the council file for the available drawings, reports and decisions.
Source records and verification details
Change record: Council portal · source SHA-256: 49ad93ea8c69123d4570e7557b959e69acf491e47f4ffce88e38dac78ccb9648
Proposal: Council portal · source SHA-256: 49ad93ea8c69123d4570e7557b959e69acf491e47f4ffce88e38dac78ccb9648
Latest source observation retained: 2026-09-21T10:12:43.436885+00:00. Source dataset date: not supplied.
Full description from the council file
20. The construction of the proposed development shall be managed in accordance with a Construction Management Plan, which shall be submitted to, and agreed in writing with, the planning authority prior to commencement of development. This plan shall provide details of intended construction practice for the proposed development, including:
(a) The location of the site and materials compound(s), including area(s) identified for the storage of construction refuse.
(b) The location of areas for the construction site offices and staff facilities.
(c) Details of site security fencing and hoardings.
(d) Details of on-site car parking facilities for site workers during the course of construction.
(e) Details of the timing and routing of construction traffic to and from the construction site and associated directional signage, to include proposals to facilitate the delivery of abnormal loads to the site.
(f) Measures to obviate the queuing of construction traffic on the adjoining road network.
(g) Measures to prevent the spillage or deposit of clay, rubble or other debris on the public road network.
(h) Alternative arrangements to be put in place for pedestrians and vehicles in the case of the closure of any public road or footpath during the course of site development works.
(i) Details of appropriate mitigation measures for noise, dust and vibration, and monitoring of such levels.
(j) Containment of all construction-related fuel and oil within specially constructed bunds to ensure that fuel spillages are fully contained. Such bunds shall be roofed to exclude rainwater.
(k) Off-site disposal of construction/demolition waste and details of how it is proposed to manage excavated soil.
(I) Means to ensure that surface water run-off is controlled such that no silt or other pollutants enter local surface water sewers or drains.
(m) A record of daily checks that the works are being undertaken in accordance with the Construction Management Plan shall be made available for inspection by the planning authority.
Reason: In the interest of amenities, public health and safety and environmental protection.
Source: local authorities / National Planning Applications. Contains Irish Public Sector Data licensed under CC BY 4.0 where supplied by NPAD. Linked documents may have separate reuse terms.