Planning near you · Donegal · Ref 2561152

A PERIOD OF 10 YEARS FOR DEVELOPMENT AT THE EXISTING ESB NETWORKS 110KV LETTERKENNY…

LISTELLIAN , LETTERKENNY , CO. DONEGAL

Appeal decision: CONDITIONAL (2026-09-14)

Applicant
Not supplied in our sources
Proposed use
See council description

The story so far

Application timeline

Recorded milestones for this application. A permission is not evidence that building work has started.

  1. Application received
    Source: NPAD

    NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68 · field: ReceivedDate

  2. Council decisionGranted with conditions
    Source: NPAD

    NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68 · field: DecisionDate

  3. Appeal submitted
    Source: NPAD

    NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68 · field: AppealSubmittedDate

  4. Appeal decisionGranted with conditions
    Source: NPAD

    NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68 · field: AppealDecisionDate

What changed

First retained observation; this does not establish that the application is new.

Observed: 23 September 2026. This describes our archive, not an application event date.

Why it matters locally

The proposal concerns LISTELLIAN , LETTERKENNY , CO. DONEGAL. Proposal excerpt: “A PERIOD OF 10 YEARS FOR DEVELOPMENT AT THE EXISTING ESB NETWORKS 110KV LETTERKENNY SUBSTATION WHICH WILL CONSIST OF: (1) SOUTHWARD EXTENSION OF THE EXISTING ESB NETWORKS 110KV SUBSTATION COMPOUND BY 0.9HA, (2) CONSTRUCT…” The appeal outcome is recorded separately from the council decision; the council decision alone gives an incomplete history.

Location & nearby applications

LISTELLIAN , LETTERKENNY , CO. DONEGAL

The marker is the source location, not the site boundary. Open larger map · Map © OpenStreetMap contributors.

Nearby applications

Closest retained records in this county within 5 km, measured between map points. Proximity does not establish a shared site.

Documents & sources

Donegal County Council · Reference 2561152

View council file →

Individual document links are not available in this retained record. Use the council file for the available drawings, reports and decisions.

Source records and verification details

Change record: NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68

Proposal: NPAD · source SHA-256: c7e82ca98b97a002e02cd996e0da83ea0362e7351d9a6edfef562ca948e47d68

Latest source observation retained: 2026-09-23T08:11:40.097106+00:00. Source dataset date: 2026-09-22.

Full description from the council file
A PERIOD OF 10 YEARS FOR DEVELOPMENT AT THE EXISTING ESB NETWORKS 110KV LETTERKENNY SUBSTATION WHICH WILL CONSIST OF: (1) SOUTHWARD EXTENSION OF THE EXISTING ESB NETWORKS 110KV SUBSTATION COMPOUND BY 0.9HA, (2) CONSTRUCTION OF A 110 KV (KILOVOLT) GAS INSULATED SWITCHGEAR (GIS) BUILDING (APPROXIMATELY 82.5M BY 18.5M) MAXIMUM HEIGHT 18.0M, TO REPLACE THE EXISTING 110KV AIR INSULATED SWITCHGEAR (AIS) SUBSTATION, (3) CONSTRUCTION OF 5 NO. 110 KV LINE CABLE INTERFACE MASTS (LCIMS) TO THE SOUTH AND SOUTH-WEST OF THE EXISTING AIS SUBSTATION COMPOUND AND PROPOSED REPLACEMENT GIS BUILDING, WHICH WILL COMPRISE THE END POINT OF THE EXISTING OVERHEAD LINE CIRCUITS ACCESSING THE PROPOSED GIS BUILDING, (4) CONNECTION OF EXISTING TRANSMISSION CIRCUITS TO THE PROPOSED GIS BUILDING BY WAY OF UNDERGROUND CABLES FROM THE NEW LCIMS, (5) DECOMMISSIONING AND REMOVAL OF 7 NO. EXISTING 110 KV TOWERS AND 3 NO. 110KV H POLES, CABLING, BUSBARS, SWITCHGEARS AND SUPPORT STRUCTURES, (6) ERECTION OF 3 NO. LIGHTNING MASTS AT 11M HIGH AT THE REPLACEMENT GIS COMPOUND, (7) TEMPORARY WIDENING (31M) OF THE EXISTING (4M) FIELD GATE ENTRANCE OFF THE L1054 TO FACILITATE A TEMPORARY CONSTRUCTION ACCESS TRACK (204M), PERMANENT ACCESS TO THE DEVELOPMENT WILL CONTINUE AS EXISTING FROM THE SUBSTATION ENTRANCE OFF THE N13 AND (8) ALL ASSOCIATED AND ANCILLARY WORKS, INCLUDING ASSOCIATED GROUND CABLING AND EARTHGRID, 5 NO. CAR PARKING SPACES, SURFACE WATER DRAINAGE, UNDERGROUND WASTEWATER STORAGE TANK, LIGHTING, LANDSCAPING AND BOUNDARY TREATMENT, SITE PREPARATION, SITE CLEARANCE AND LEVELLING, PROVISION OF HARDSTANDING, PERMANENT INTERNAL ACCESS ROAD (505M), 1 NO. TEMPORARY CONSTRUCTION COMPOUND AND 1 NO. TEMPORARY LAYDOWN AREA WITH 20 NO. TEMPORARY CAR PARKING SPACES AND ALL ANCILLARY WORKS, ON AN OVERALL SITE AREA OF 9.3HA. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
Application details
Reference
2561152
Site address
LISTELLIAN , LETTERKENNY , CO. DONEGAL
Homes in source field
0 (proposal, not completions)
Reported floor area (m²)
0
Application type
PERMISSION
Latest reported outcome
Appeal decision: CONDITIONAL (2026-09-14)
Date received
July 07, 2025
Decision due
August 31, 2025
Council decision date
August 28, 2025
Authority
Donegal County Council

Source: local authorities / National Planning Applications. Contains Irish Public Sector Data licensed under CC BY 4.0 where supplied by NPAD. Linked documents may have separate reuse terms.