Wicklow County Council has drawn down just €458,588 of €6.45m allocation for new public transport bridge

By Hugh O'Farrell Walsh, The Wicklow People

The Wicklow People

A long-promised public transport bridge, intended to reshape mobility between Bray and the rapidly expanding Fassaroe strategic development zone, has stalled again, with new figures showing no progress and no funding drawn down in 2026.

The bridge, backed by a €6.45 million allocation under the Urban Regeneration and Development Fund (URDF), was meant to provide a dedicated link across the River Dargle for buses, pedestrians and cyclists, forming the backbone of a new east–west transport corridor.

Instead, it remains stuck at early design stage, leaving a completed park and ride idle and thousands of planned homes in Fassaroe without the public transport spine they were promised.

New government data confirms the scale of the stagnation. Wicklow County Council has drawn down just €458,588 of the €6.45 million allocation since the project was approved, and nothing at all this year.

The bridge is planned to cross the River Dargle west of Bray town centre, linking the Little Bray side near Dargle Road and Ravenswell to the Fassaroe park and ride and the new main street spine.

This corridor was identified years ago by the National Transport Authority as the only viable non motorway link between Bray and Fassaroe, bypassing the N11/M11 entirely.

The motorway currently acts as a hard barrier, forcing all movement between the two areas through congested junctions. The bridge was designed to break that dependency, allowing buses to run directly from Fassaroe into Bray town centre without touching the N11.

That direct connection was supposed to be in place before largescale housing arrived. However, construction in Fassaroe is advancing, while the transport infrastructure lags far behind. More than 4,000 homes are planned for the area, and enabling works have already been funded through the Housing Infrastructure Initiative Fund.

The park and ride, built and finished at significant cost, sits unused because the bus corridor and bridge it was meant to serve do not exist.

The bridge is also important for the Luas extension to Bray, now pushed into the mid 2030s. Designs show that it will be built to accommodate the new transport link.

The bridge requires complex engineering across a sensitive floodplain, a factor that has repeatedly slowed progress.

The River Dargle is one of the most heavily modelled rivers in the region, and any new structure must undergo detailed hydraulic analysis, flood risk assessment, and scenario testing to ensure it does not worsen downstream flooding or interfere with the existing Dargle flood defence scheme.

That modelling must be signed off by multiple agencies, adding layers of technical review before a design can even be finalised.

The project also involves coordination with several landowners on both sides of the river, including parcels earmarked for future development in Fassaroe and long-established residential areas in Little Bray.

Securing access, agreeing alignments, and resolving boundary issues have proven slow, with negotiations continuing in parallel to the design work.

Compounding the technical challenges is strong opposition from local residents, particularly on the Little Bray side, where concerns have been raised about increased bus traffic, loss of green space, visual impact, and potential flood implications.