The Supreme Court has granted Save the South Leinster Way and Tara Heavey leave to appeal in their wind farm planning challenge, on 9 February 2024.
An Bord Pleanála granted permission for 21 wind turbines on 22 September 2022. The planning law gave eight weeks to challenge that decision. Springfield Renewables Limited is the notice party.
The group issued its proceedings on 21 November 2022, which was eight weeks and one day after the permission. It did not seek an extension of time.
Humphreys J. refused to extend time in the High Court. He said the applicants could have acted sooner, and that a lawyer's error is not normally good and sufficient reason for an extension.
The group applied for leave on 8 January 2024, which was out of time. The Supreme Court extended time.
An Bord Pleanála accepted that the case raises questions of general importance. It said clarifying the law would be very helpful to the planning system.
Charleton J, Murray J and Donnelly J said the High Court judgment deals with a small but significant point. They said time limits set by statute are central to the swift disposal of planning cases.
Leave was granted on two issues. The first is whether a time limit that expires on a Sunday or other non-working day extends to the next working day. The second is whether the application is moot and should not be decided.
The court said the case is so self-contained that it may be dealt with on written submissions only. That will be addressed at case management.