The court will hear one point only, on whether An Bord Pleanála's reasoning was sufficient, and it may wait for the outcome of Connelly v An Bord Pleanála.

The Supreme Court will hear an appeal by the North Kerry Wind Turbine Awareness Group over planning permission for a windfarm. It granted the group leave on 9 October 2017, to appeal directly from the High Court.

The group challenged An Bord Pleanála's decision to give permission. McGovern J. refused its application for an order of certiorari on 9 March 2017, and on 2 May 2017 refused a certificate of leave to appeal. Kerry County Council, Ireland, the Attorney General and Stacks Mountain Windfarm Limited are notice parties.

The Supreme Court did not accept that the group had met the constitutional criteria on its point about material contravention of the county development plan. It said the group had not defined the issue it said arose.

Leave was granted on one question: whether, in all the circumstances, the Board's reasoning and analysis were sufficient. The group argued that the standard applied in Connelly covers both environmental impact assessment and appropriate assessment. It pointed to a reference to the Court of Justice of the European Union made by Humphreys J. in Holohan v An Bord Pleanála, and to the Supreme Court's decision to hear Connelly v An Bord Pleanála.

McGovern J. had found that the Board carried out an appropriate assessment and that it was sufficiently recorded. He did not apply the standards from the High Court's Connelly decision, since the Board was seeking leave to appeal it.

The court said Connelly has been given priority, so its outcome may affect when this appeal is listed.