Courts / Meath / Report

Challenge to proposed data centre that will generate 1% of Ireland's carbon emissions dismissed

Date
2023-07-21
Stage
Hearing Or Decision
Primary locality
Clonee
County
Meath

Summary

In a High Court decision on 21 July 2023, the challenge by Mannix Coyne and his daughter Amy Coyne to the approval of a 180‑megawatt data centre near their home in Bracetown, Clonee, Co. Meath, was dismissed. The Coynes alleged that the centre would produce about 1% of Ireland's annual CO₂ emissions and that the planning permission granted in July 2021 breached their constitutional rights to a healthy environment and other rights under the European Convention on Human Rights. They also claimed the decision violated planning regulations, the 2000 Planning and Development Act, the EU Directive on Environmental Impact Assessments and Habitats, and the 2015 Climate Action and Low Carbon Development Act, and that it would harm their equine business. The State, An Bord Pleanala and EngineNode Ltd rejected all claims, arguing that a right to a healthy environment is not recognised under the Constitution or the ECHR.

Who, what, where, when and why

What: Report matter: Challenge to proposed data centre that will generate 1% of Ireland's carbon emissions dismissed. Procedural stage: hearing_or_decision

When:

Case subjects

Amy Coyne

Applicant

Places mentioned

Court Venue
  • High Court
Secondary Mention
Residence

Topics

Stage Hearing Or Decision

Related court reports

Read the original CNI report

Correction or retraction request

If a fact, identity, locality or legal outcome needs review, email the newsroom with this report's details prefilled.