Vaccine plant construction severely delayed by dispute, High Court told

Date
2021-06-11
Stage
Hearing Or Decision
Primary locality
Dundalk
County
Louth

Summary

In a High Court hearing on 11 June 2021, Sepam Solutions Limited, contracted to supply plumbing, mechanical and electrical works for a vaccine plant at the IDA Science and Technology Park in Dundalk, claimed that its subcontractors MDLR Ltd and Titin Ltd had breached their agreements. Sepam alleged that MDLR had retained essential equipment supplied by the plaintiff, while Titin had refused to return an €830,000 down payment made for specialised materials. The dispute has caused a delay of 12 to 16 weeks in the plant's construction, which is intended to produce Dengue fever vaccines for Merck, Sharp & Dohme. Sepam seeks an injunction ordering the defendants to return the equipment and the down payment, and to prevent them from reducing the value of their assets below €830,000. Mr Justice Senan Allen granted Sepam permission to serve a short notice of the injunction application, with the case set to return later in the month.

Who, what, where, when and why

What: Report matter: Vaccine plant construction severely delayed by dispute, High Court told. Procedural stage: hearing_or_decision

When:

Case subjects

Ida Science

Applicant

Places mentioned

Court Venue
  • High Court
  • Dohme. In High Court
Address Area
  • Technology Park

Topics

Stage Hearing Or Decision

Related court reports

Read the original CNI report

Correction or retraction request

If a fact, identity, locality or legal outcome needs review, email the newsroom with this report's details prefilled.

Email a correction request