Courts / Louth / Report
Vaccine plant construction severely delayed by dispute, High Court told
Summary
In a High Court hearing on 11 June 2021, Sepam Solutions Limited, contracted to supply plumbing, mechanical and electrical works for a vaccine plant at the IDA Science and Technology Park in Dundalk, claimed that its subcontractors MDLR Ltd and Titin Ltd had breached their agreements. Sepam alleged that MDLR had retained essential equipment supplied by the plaintiff, while Titin had refused to return an €830,000 down payment made for specialised materials. The dispute has caused a delay of 12 to 16 weeks in the plant's construction, which is intended to produce Dengue fever vaccines for Merck, Sharp & Dohme. Sepam seeks an injunction ordering the defendants to return the equipment and the down payment, and to prevent them from reducing the value of their assets below €830,000. Mr Justice Senan Allen granted Sepam permission to serve a short notice of the injunction application, with the case set to return later in the month.
Who, what, where, when and why
What: Report matter: Vaccine plant construction severely delayed by dispute, High Court told. Procedural stage: hearing_or_decision
When:
- 2021-06-11 Publication
Case subjects
Applicant
Places mentioned
- High Court
- Dohme. In High Court
- Technology Park
Topics
Related court reports
- Worker sacked over punch-up with takeaway driver wins job back
- Legal first sees miscarriage of justice certificate for IRA membership conviction quashed
- Lorry driver who imported €1m in cannabis jailed for five years
- Explosive device allegedly stored in National Museum at Collins' Barracks
- On-bail home invader who dragged car owner along ground has sentence cut
- Amateur fighter who 'brutally killed' allegedly abusive mother - kicking her to death and stepping on her 'lifeless body' as he left her to die - gets 6.5 years
If a fact, identity, locality or legal outcome needs review, email the newsroom with this report's details prefilled.
Email a correction request