In the Commercial Court, Mr Justice Brian McGovern has fast‑tracked two environmental challenges to windfarm projects in the south of Ireland. The first case concerns Peter Sweetman's objection to Tipperary County Council's extension of planning permission for a 16‑turbine windfarm at Castlewaller, Newport. Sweetman questions the viability of the €46 million project, which was originally approved in 2012 and extended in July. The council's developer, Castlewaller Woodland and Partnership (CWP), argues the extension is necessary for the project to qualify for the REFIT II state financial support scheme and for the creation of 30–40 construction jobs and 7 full‑time positions. The case is scheduled to return to court in May. The second fast‑tracked case involves the North Kerry Wind Turbine Awareness Group challenging An Bord Pleanala's permission for 10 turbines near Lixnaw, Kerry. The challenge cites non‑compliance with the Environmental Impact Assessment Directive and the EU Habitats Directive.
Who, what, where, when and why
What: Report matter: Windfarm challenges fast-tracked. Procedural stage: hearing_or_decision
When:
- 2016-11-16 Publication
Why: That action, which has also been adjourned, to has been brought because of concerns that any serious delay on the proposal will seriously jeopardise that schemes participation in the REFIT II scheme. CNI source report
Case subjects
Applicant
Outcome: That action, which has also been adjourned, to has been brought because of concerns that any serious delay on the proposal will seriously jeopardise that schemes participation in the REFIT II scheme.
Applicant
Outcome: That action, which has also been adjourned, to has been brought because of concerns that any serious delay on the proposal will seriously jeopardise that schemes participation in the REFIT II scheme.
Applicant
Outcome: That action, which has also been adjourned, to has been brought because of concerns that any serious delay on the proposal will seriously jeopardise that schemes participation in the REFIT II scheme.
Applicant
Outcome: That action, which has also been adjourned, to has been brought because of concerns that any serious delay on the proposal will seriously jeopardise that schemes participation in the REFIT II scheme.
Places mentioned
Topics
Related court reports
- Jailed rapist fails to convince court that 8.5-year sentence was too severe
- Cross-examination of abuse complainants cannot 'pry unnecessarily' into their personal lives, Court of Appeal finds
- Rapist 'should have protected his younger brother'
- Bothar wants to join estate of late founder to proceedings
- Former Bóthar CEO, who admits misappropriating huge sums, wants free legal aid
- Bóthar CEO 'stole' from charity for 21 years to fund lifestyle, High Court hears
If a fact, identity, locality or legal outcome needs review, email the newsroom with this report's details prefilled.
Email a correction request